+90 530 664 2263
Blog

Industrial Facility As-Built Modeling: Process and Challenges | Eos Proje

Industry ApplicationsJanuary 12, 20265 min read

Industrial Facility As-Built Modeling

Analitik Özet

TL;DR: As-built BIM modeling in industrial facilities (factories, refineries, power plants) is 300% more complex than standard buildings: Dense MEP systems (pipe density 15-25 m/m²), working in active production environment, safety protocols. Our Toyota Factory project: 50,000 m² facility, 2,500+ MEP elements, LOD 300, 8 weeks. Success keys: Detailed planning + experienced team + phased approach.

Unique Challenges of Industrial Facilities

1. MEP System Density

Standard Office Building: 3-5 meters pipe/m²

Industrial Facility: 15-25 meters pipe/m² (5-8x denser!)

In our Toyota project, in process area alone:

800+ pipe runs (DN25-DN800)
350+ valves
150+ equipment (tanks, pumps, heat exchangers)
200+ instrumentation points

Pipe Complexity: In one process unit, 6 different systems together: Process fluid, cooling water, steam, compressed air, chemical drain, fire fighting. Each with different material, pressure rating, insulation requirement.


2. Working in Active Production Environment

Factories operate 24/7 - how is laser scanning done?

#### Strategies:

A. Outside Shift Hours:

Night 00:00-06:00
Minimize production downtime
Reduce safety risk

B. Modular Approach:

Factory scanned zone by zone
Critical production areas on weekends
Non-critical areas during normal hours

C. Remote Scanning:

Hazardous areas (high temperature, chemical risk)
Drone-based scanning (outdoor areas)

3. Safety Protocols

Safety is paramount in industrial facilities:

RequirementDetail
HSE TrainingMinimum 8 hours site-specific
PPEHelmet, safety shoes, goggles, earplugs
Gas DetectionPersonal H2S, LEL detectors
PermitsWork permit, hot work permit (if required)
EscortsProduction team escort mandatory

Industrial As-Built Modeling Process

Phase 1: Pre-Project Planning (1-2 weeks)

Client briefing + site visit
Existing documentation review (P&IDs, isometrics)
Safety training
Scan planning (zone division)
Deliverable: Project Execution Plan (PEP)

Phase 2: Laser Scanning (3-7 days)

Scan Density Requirements:

Process piping areas: 3-5mm
Structural steel: 5-10mm
General areas: 10-15mm

Toyota Project Stats:

250+ scan positions
45 TB raw data
5 billion points
Accuracy: ±3mm global registration

Phase 3: Point Cloud Processing (1 week)

Unique challenges in industrial facilities:

Hot Equipment: Laser beams scatter from hot surfaces (300°C+) → noise

Solution: Consider shutdown plans or prioritize cold areas

Reflective Surfaces: Stainless steel tanks, polished pipes → multiple reflections

Solution: Target-based registration + increased overlap

Vibration: Rotating equipment vibration → blurred points

Solution: Equipment shutdown or average multiple scans


Phase 4: BIM Modeling (4-6 weeks)

#### Modeling Priorities:

Week 1-2: Structural & Equipment

Steel structure (columns, beams, platforms)
Major equipment (tanks, vessels, pumps)
Equipment foundations

Week 3-4: Piping Systems

Main process lines (critical diameters DN150+)
Headers and risers
Pipe supports

Week 5-6: Secondary Systems & Details

Small bore piping (DN50 and below)
Instrumentation
Cable ways
Fire fighting system

Phase 5: QA/QC (1 week)

Critical Checks:

[ ] Pipe connectivity (inlet/outlet match)
[ ] Elevation verification (±10mm)
[ ] Flange-to-flange dimensions
[ ] Equipment nozzle orientations
[ ] Clash detection (hard clashes = 0)
[ ] P&ID reconciliation

On the Polyol Thyssenkrupp project, we reconciled 450+ pipe connections with P&ID. Found 12 discrepancies - after field verification, P&ID was updated. BIM model caught P&ID errors.

U

UÄŸur Bilen

Eos Proje


Sector-Specific Considerations

Petrochemical / Refinery

Characteristics:

High pressure/temperature lines
Exotic materials (Hastelloy, Inconel)
Complex instrumentation
Flare systems

LOD: 350-400 (fabrication required)


Power Plant (Linde Tiszaujvaros)

Characteristics:

Large diameter piping (DN600-DN1200)
Insulation modeling (100-200mm thick)
Cable tray networks
HVAC systems (large duct sizes)

LOD: 300-350


Manufacturing Facility (Toyota, Şişecam)

Characteristics:

Process equipment chains
Conveyor systems
Utility distribution
Clean room requirements (if applicable)

LOD: 300


Frequently Asked Questions

Sıkça Sorulan Sorular

150-250% more expensive because:

- MEP density 5-8x higher

- Safety requirements & training

- Complex geometry (pipe routing)

- Specialized expertise (process knowledge)

- More intensive QA/QC

Cost per m²: $2.35-3.90/m² (LOD 300, MEP included) vs. office building $1.30-1.80/m²

Yes, possible but:

- Strict compliance with HSE protocols

- Critical coordination with production team

- Phased approach (zone by zone)

- Night shifts or weekend work

- Some areas may require shutdown

On Toyota project, 80% of areas scanned under active production, 20% planned shutdown.

Tolerance levels for LOD 300:

- Horizontal position: ±10-15mm

- Elevation: ±10mm

- Pipe diameter: Nominal (accurate)

- Flange-to-flange: ±5mm

For critical tie-in points (existing+new), ±5mm recommended.

P&ID (Piping & Instrumentation Diagram): Process flow schematic

Reconciliation: Comparing BIM model with P&ID

- Is as-built actually compliant with P&ID?

- Are modifications captured?

- Is instrumentation complete?

Why Important: P&ID is operational critical document. Must be in sync with as-built BIM. We find 5-10% discrepancies in our projects (P&ID usually outdated).

| Software | Best For | Strengths |

|---------|----------|-----------|

| Revit | General industrial | Common, IFC export |

| AutoCAD Plant 3D | Process plants | P&ID integration |

| PDMS/E3D | Large refineries | Advanced piping tools |

| Navisworks | Coordination | Clash detection |

Eos Proje uses: Revit (modeling) + Navisworks (QA/QC) combo.


Related Case Studies:


Last Updated: January 25, 2026

Author: UÄŸur Bilen

Category: Industry Applications | Reading Time: ~8 minutes